In the Input section, you can add the materials required for the Job Order. The materials can be added using three methods:
The user can retrieve the materials list for that Job Order according to the BOM of the Design. Using Auto Generate Plan, the user can get the materials list automatically from the BOM of that design, along with the required quantities.
This method also generates the list of materials using the BOM of that Design. The difference from Auto Generate Plan is that in Add Stock From BOM, the user can change the required quantity for each material. This is done for processes where more material is required to complete the process.
For example, in casting, you need to add some extra metal than required for that cast.
This method is can be used to add materials individually, without the BOM.
Material can be added using Add Material method in three different ways: